Implementation Plan
This plan sets several milestones for tasklist
module development. It does not cover QA, documentation
and other related tasks.
Prototype Milestone
Date: 2nd December 2003
Dependencies: UI specification
Criteria: demoable functionality
Prototype implementation of all functionality
providing usability and perceived performance feedback.
Review Report
Beta Milestone
Date: 16th December 2003
Dependencies: communicated at all levels
Criteria: module added to regular build
Code stabilized to such level that
it can be passed to QA testing.
Unit tests in place.
Report
Freeze Milestone
Date: 9th January 2004
Dependencies: graphics delivered, functionality tests written
Criteria: test specification passed
Code internationalized, performance addressed,
dirty hacks removed or evaluated. No enhacements
behind this point only bug fixing. Code base
prepared for freeze branching. Final module
packaging layout.
Report
Tested Milestone
Date: 21th January 2004
It's the second attempt to match
Freeze Milestone criteria.
Petr Kuzel on 9th January 2004